Routed, Planned, & Moving Along

Upcoming Milestones 2026-2029

2027

RioSol Starts Construction

SouthWestern Power Group expects to start full construction of RioSol.

2029

RioSol Starts Operating

SouthWestern Power Group expects to complete construction and start operation of RioSol.

2029

Operation Begins

SouthWestern Power Group expects to complete construction and start operation of RioSol.

2027

Construction Starts

SouthWestern Power Group expects to start full construction of RioSol.

2024

$2.4 Billion Economic Benefit Report Published

RioSol will create $2.4 billion economic impact and generate 2,626 jobs.

2023

New Mexico Renewable Transmission Authority development partner

SouthWestern Power Group and New Mexico Renewable Transmission Authority sign a joint-development agreement for RioSol line.

 

Amended Federal Record of Decision

The Department of the Interior’s Bureau of Land Management announced a Record of Decision.

2022

Line 2 renamed RioSol

SouthWestern Power Group renames Line 2 RioSol. Line 1 sold to Pattern Energy.

 

Revised Draft Environmental Impact Statement Issue

Bureau of Land Management issues the Draft Environmental Impact Statement for the re-routed Project.

2020

Federal Permit is reopened

SouthWestern Power Group submits an amended SF-299 to the Bureau of Land Management to re-start federal permitting for the re-routed portion of the Project.

2019

Line 1 changes to HVDC

Line 1 changes to HVDC; Line 2 remains HVAC.

2018

SouthWestern Power Group and the US Military agree on the re-route

SouthWestern Power Group and the Dept of Defense agree to re-route a portion of the line in NM that avoids the Northern Call-Up area, north of WSMR.

2016

SouthWestern Power Group selects Anchor Tenant

SouthWestern Power Group selects Pattern Energy as anchor tenant for Line 1.

 

Arizona State Permit is granted

The Arizona Corporation Commission approves a Certificate of Environmental Compatibility for the Project.

2015

Federal Permit is granted

The Bureau of Land Management issues the Record of Decision for the Project

2011

Federal Energy Regulatory Commission approves cost recovery

Federal Energy Regulatory Commission approves SouthWestern Power Group’s request for negotiated rate authority.

2008

Federal Permitting Starts for Two HVAC Lines

SouthWestern Power Group submits an SF-299 to the Bureau of Land Management to commence federal environmental permitting under NEPA.

Joint Development Agreement signed

SouthWestern Power Group and 4 other companies signed a joint development agreement for Southwest Transmission Project.

2006

Start of Project Development

SouthWestern Power Group (SWPG) starts planning the development of an interstate transmission project between AZ and NM consisting of two, single-circuit 500kV transmission lines and associated substations.