Routed, Planned, & Moving Along
Upcoming Milestones 2026-2029
2027
RioSol Starts Construction
SouthWestern Power Group expects to start full construction of RioSol.
2029
RioSol Starts Operating
SouthWestern Power Group expects to complete construction and start operation of RioSol.
2029
Operation Begins
SouthWestern Power Group expects to complete construction and start operation of RioSol.
2027
Construction Starts
SouthWestern Power Group expects to start full construction of RioSol.
2024
$2.4 Billion Economic Benefit Report Published
RioSol will create $2.4 billion economic impact and generate 2,626 jobs.
2023
New Mexico Renewable Transmission Authority development partner
SouthWestern Power Group and New Mexico Renewable Transmission Authority sign a joint-development agreement for RioSol line.
Â
Amended Federal Record of Decision
The Department of the Interior’s Bureau of Land Management announced a Record of Decision.
2022
Line 2 renamed RioSol
SouthWestern Power Group renames Line 2 RioSol. Line 1 sold to Pattern Energy.
Â
Revised Draft Environmental Impact Statement Issue
Bureau of Land Management issues the Draft Environmental Impact Statement for the re-routed Project.
2020
Federal Permit is reopened
SouthWestern Power Group submits an amended SF-299 to the Bureau of Land Management to re-start federal permitting for the re-routed portion of the Project.
2019
Line 1 changes to HVDC
Line 1 changes to HVDC; Line 2 remains HVAC.
2018
SouthWestern Power Group and the US Military agree on the re-route
SouthWestern Power Group and the Dept of Defense agree to re-route a portion of the line in NM that avoids the Northern Call-Up area, north of WSMR.
2016
SouthWestern Power Group selects Anchor Tenant
SouthWestern Power Group selects Pattern Energy as anchor tenant for Line 1.
Â
Arizona State Permit is granted
The Arizona Corporation Commission approves a Certificate of Environmental Compatibility for the Project.
2015
Federal Permit is granted
The Bureau of Land Management issues the Record of Decision for the Project
2011
Federal Energy Regulatory Commission approves cost recovery
Federal Energy Regulatory Commission approves SouthWestern Power Group’s request for negotiated rate authority.
2008
Federal Permitting Starts for Two HVAC Lines
SouthWestern Power Group submits an SF-299 to the Bureau of Land Management to commence federal environmental permitting under NEPA.
Joint Development Agreement signed
SouthWestern Power Group and 4 other companies signed a joint development agreement for Southwest Transmission Project.
2006
Start of Project Development
SouthWestern Power Group (SWPG) starts planning the development of an interstate transmission project between AZ and NM consisting of two, single-circuit 500kV transmission lines and associated substations.
