view alternate design
Routed, Planned, & Moving Along
Current 2023
February 2023
Revised Final EIS issued
FutureĀ 2023-2028
April 2023
Amended Federal Record of Decision
Amended Federal Record of Decision Expected.
Mid-to-Late 2023
Start of Line 1 Construction
Pattern Energy expects to start full construction of Line 1.
Late 2025
Line 1 starts Operating
Pattern Energy expects to complete construction and start operation of Line 1.
Late 2025
RioSol/Line 2 starts Construction
SWPG expects to start full construction of RioSol (Line 2).
Early – Mid 2028
RioSol/Line 2 starts Operating
SWPG expects to complete construction and start operation of RioSol (Line 2).
PastĀ 2006-2022
December 2022
Line 2 renamed RioSol
SWPG renames Line 2 RioSol to avoid confusion with Line 1 which is called SunZia.
July 2022
Line 1 is sold to Pattern Energy
SWPG sells SunZia Line 1 to Pattern Energy and keeps Line 2.
May 2022
Revised Draft EIS issued
BLM issues the Draft EIS for the re-routed Project.
April 2021
NMRETA joins SunZia as co-development partner
SunZia and NMRETA sign a joint-development agreement.
December 2020
Federal Permit is re-opened
SunZia submits an amended SF-299 to the BLM to re-start federal permitting for the re-routed portion of the Project.
Mid-2019
Line 1 changes to HVDC
SunZia and Pattern Energy agree to change the technical basis for Line 1 from HVAC to HVDCwith 3,000 MW of capacity. Line 2 will now be HVAC with 1,500 MW of capacity.
November 2018
SunZia and US Military agree on re-route
SunZia and the Dept of Defense agree to re-route a portion of the line in NM that avoids the Northern Call-Up area, north of WSMR.
August 2016
SunZia selects Anchor Tenant
The Project selects Pattern Energy as anchor tenant for Line 1.
February 2016
Arizona State Permit is granted
The Arizona Corporation Commission approves a Certificate of Environmental Compatibility for the Project.
January 2015
Federal Permit is granted
The BLM issues the Record of Decision for the Project.
May 2011
FERC approves SunZia cost recovery
FERC approves negotiated rate authority for Line 1.
September 2008
Federal Permitting starts
The Project submits an SF-299 to the BLM to commence federal environmental permitting under NEPA.
April 2008
Joint Development Agreement signed
SWPG and 4 other companies signed a joint development agreement for the SunZia Southwest Transmission Project.
Summer 2006
Start of Project Development
SouthWestern Power Group (SWPG) started planning the development of an interstate transmission project between AZ and NM consisting of two, single-circuit 500kV transmission lines and associated substations.